Church Extension - "The Wesley Suite"
Background It had long been the wish of the Church Council to have toilet and kitchen facilities available on site, instead of having to use the nearby village hall. Earlier proposals only got as far as sketch plans when it became necessary to replace the complete heating system, putting plans for the extension on hold.
The joining together of the Anglican and Methodist Churches in the village meant that the Methodist chapel was no longer needed, and was subsequently sold. The Methodist Church had agreed that the proceeds from the sale could remain in the parish, but could only be used to replace facilities lost when the chapel closed. As the chapel had toilets, a kitchen and a hall, the proposed extension fitted the criteria perfectly.
Timeline March 2011 .... Architect receives tenders from selected builders. April .... . . . ..... Preferred tender/builder selected by Church Council . ......... ..... . . . . Pre-contract meeting held with builder 23 May ... . . . . Builders arrived on site. 27 May .... . . . Demolition started on the old boiler house & store shed.
31 May ... . . . . Chimney and rendering removed. 3 June .... . . . . Temporary entrance made in hedge 7 June ..... .. . . Site levelled & footings dug
10 June ... Foundations laid
17 June ... Drainage work complete 22 June ... Walls to floor level 23 June ... Pews removed from west end of North Aisle
28 June ... Floor laid
30 June . . Stone plinth complete 1 July ...... West wall pinned prior to inserting doorway
4 - 7 July ....... Doorway made in west wall
7 July ........ Time Capsule placed under floor of Meeting Room by Primary School pupils. 12 July ...... The building started to take shape
14 July . . . . Work continued on the framework
14 July .......... Framework almost complete
21 July. . . . . . Work started on the exterior cladding
25 July . . . . . . . . . Cladding continued
4 August .............. Exterior ready to receive slates
6 August . . . . . . . Floor insulation laid & partitions erected
8 August . . . . . . Underfloor heating installed
12 August . . . . . Flooring screed laid, main window installed, 1st fix electrics underway
19 August . . . . . . Work started on cladding the walls with slates
27 August .. . . . . . Slate cladding on walls almost completed
11 September . . . . . Slating & glazing complete, plasterboard applied to interior walls.
24 September .... . . . Nearing completion - Meeting Room & Looking into the church
24 September . . . . . Looking from the church into the extension
26 September . . . . . . . Donated kitchen waiting to be installed
29 September . . . . . . . Inspecting the hatch doors ![]() 30 September . . . . . . Front door and cladding fitted. Scaffolding removed
6 October ..... ...... Churchyard lighting installed
13 October ............. Toilets completed
20 October ... ........... Meeting Room & Kitchen completed
30 October ................. Messy Church - new extension used for the first time
|
|||||||
| Services | ||||||||
| News | ||||||||
| Tour | ||||||||
| Activities | ||||||||
| The Church | ||||||||
| Churchyard | ||||||||
| Who's Who | ||||||||
| Photo Album | ||||||||
| Anglican/Methodist Partnership | ||||||||
| Extension | ||||||||
| Links | ||||||||
| Christmas Tree Festival | ||||||||